  • See the progress!

    Building “A” and “B” are now 95% completed!- please see the progress by comparing our new pictures with the ones we shared last week.
    As you can see plastering of walls has gone up to 100 %. We are now moving on with painting works plus walls and roofing works are on course. We still need to connect the water and sewage lines to the Building B, as well as
    work on instillation of doors and window glasses.
    How do you like the sunny orange on the school walls? 🙂